Process for adding or changing guidelines
|
|
=========================================
|
|
|
|
This document describes the process we will use before merging a non
|
|
trivial changeset in the guidelines directory. A non trivial changeset
|
|
is one which is more than a spelling/grammar typo or reformatting
|
|
change.
|
|
|
|
The guidelines are initially intended to be a group draft document. Our intent
|
|
is to move fairly quickly to get published draft guidelines so this process
|
|
reflects a preference for efficiency while gathering consensus.
|
|
|
|
Review process
|
|
--------------
|
|
|
|
For trivial changes (as defined above) there is no minimum time that they must
|
|
be proposed before merging. They must have at least one +1 vote other than the
|
|
approver and no -1. Once this is true a working group core may merge the
|
|
change.
|
|
|
|
For changes which add a new guideline or make substantial changes to an
|
|
existing guideline reaching consensus is an explicit goal. To that end there is
|
|
a well defined process to ensure that proposals receive adequate review by the
|
|
API Special Interest Group, cross project liaisons, and the OpenStack community
|
|
at large.
|
|
|
|
In the various stages of the review process (defined below) consensus means the
|
|
changeset is in its near final form for at least two working days. Minor
|
|
typo/formatting changes do not reset the counter. There must be at least four
|
|
+1 votes and no -1 votes unless the concern related to the -1 vote has been
|
|
discussed in an API WG meeting. Once the matter has been discussed there should
|
|
be no more than 20% of votes cast as -1 votes.
|
|
|
|
Discussion on Gerrit should be encouraged as the primary response. When
|
|
discussion on IRC (in meetings or otherwise) is required that discussion should
|
|
be summarized back to Gerrit.
|
|
|
|
That process is:
|
|
|
|
1. API Special Interest Group members should review proposed guideline changes
|
|
and reach consensus.
|
|
|
|
2. When consensus is reached within the group the guideline should be marked as
|
|
*frozen* and cross project liaisons (CPLs) should be invited to review the
|
|
guideline. There is an ``add-reviewers.py`` script to do this. See
|
|
:doc:`liaisons` for more information.
|
|
|
|
A proposal can be frozen by exactly one core reviewer by setting Code-Review
|
|
+2. Only the core reviewer responsible for freezing the proposal should +2
|
|
it. All other core reviewers should vote with at most a +1 when reviewing.
|
|
|
|
3. The CPLs have one week to review the proposal. If there are no reviews lazy
|
|
consensus is assumed. If there is a -1 review by a CPL that requires an
|
|
update to the changeset, it does not reset the 1 week the CPLs have to
|
|
review it.
|
|
|
|
4. When there is consensus from the CPLs, the proposal may be merged.
|
|
|
|
To avoid opportunities for miscommunication, the core working group member
|
|
who froze the changeset should be responsible for merging it. If that core
|
|
is unavailable for enough time to cause a delay then the responsibility
|
|
falls to one of the others cores.
|
|
|
|
An email should be sent to the openstack-dev mailing list containing the
|
|
links to all of the guidelines that have recently merged. The finalized
|
|
guidelines should be buffered such that a maximum of one announcement email
|
|
is sent per week.
|
|
|
|
If at any time during this process there is difficulty reaching consensus or an
|
|
apparent lack of information or input, additional input should be sought from
|
|
the rest of the community. Two ways to do this include (preferring email):
|
|
|
|
1. The openstack-dev mailing list. An email may be sent to the openstack-dev
|
|
mailing list with the subject "[all][api] New API Guidelines Ready for Cross
|
|
Project Review". The email should contain links to the guidelines that need
|
|
additional input.
|
|
|
|
2. The `Cross Project Meeting
|
|
<https://wiki.openstack.org/wiki/Meetings/CrossProjectMeeting>`_. An agenda
|
|
item should be added to the Cross Project Meeting which indicates need for
|
|
discussion. Links to the guidelines that need additional input should be
|
|
provided. When this is done an API WG member must attend the meeting to
|
|
highlight the agenda item.
|
|
|
|
Merged guidelines comprise a draft of the official guidelines. Before an
|
|
official version of the guidelines can be released the following has to occur:
|
|
|
|
* An 80% (of votes cast) majority vote on the document as a whole with one vote
|
|
per OpenStack PTL (or delegate).
|
|
|
|
* Reviewed and approved by the TC. The API WG is a delegated group from the TC
|
|
so the TC ultimately get final say on what the working group are able to
|
|
release.
|
|
|
|
Proposing a new guideline
|
|
-------------------------
|
|
|
|
When proposing a new guideline you should start by using the :doc:`guideline
|
|
template <template>` to generate the basic structure. Copy the ``template.rst``
|
|
file to the ``guidelines`` directory with a filename reflecting your new
|
|
guideline (for example ``guidelines/errors.rst``), and then follow the
|
|
instructions within the template. Once complete you should follow the
|
|
`developer workflow`_ and the previously stated review process to have your
|
|
guideline accepted.
|
|
|
|