2024 CFN Release Timeline
Event | Dates | Relative Dates | Start Relative Dates | Description |
---|---|---|---|---|
Release Start | May. 23 | Start date | Start date | Declare Intention: Each sub-project should create or update sub-group introduction and release plan. |
Initial Checkpoint | June. 6 | Start date + 2 weeks | Start date + 2 weeks | Release plan preparation and review. |
Middle Checkpoint | Aug. 1 | Initial checkpoint + 8 weeks | Start date + 10 weeks | Progress chack. |
Code Freeze | Sep. 19 | Middle checkpoint + 7 weeks | Start date + 17 weeks | Cut and lock release branch. Any update of code after this day will NOT be included within current release. |
Final Checkpoint | Oct. 17 | Code freeze + 4 weeks | Start date + 21 weeks | Each project finish related documentation and release summry for release review. |
Fornal Release | Oct. 31 | Final checkpoint + 2 week | Start date + 23 weeks | Formal release with release tag. |