# 2024 CFN Release Timeline | Event |Dates |Relative Dates |Start Relative Dates |Description | | :--- | :--- | :--- | :--- | :--- | | Release Start |May. 23 |Start date |Start date |Declare Intention: Each sub-project should create or update sub-group introduction and release plan. | | Initial Checkpoint |June. 6 |Start date + 2 weeks |Start date + 2 weeks |Release plan preparation and review. | | Middle Checkpoint |Aug. 1 |Initial checkpoint + 8 weeks |Start date + 10 weeks |Progress chack. | | Code Freeze |Sep. 19 |Middle checkpoint + 7 weeks |Start date + 17 weeks |Cut and lock release branch. Any update of code after this day will NOT be included within current release. | | Final Checkpoint |Oct. 17 |Code freeze + 4 weeks |Start date + 21 weeks |Each project finish related documentation and release summry for release review. | | Fornal Release |Oct. 31 |Final checkpoint + 2 week |Start date + 23 weeks |Formal release with release tag. |